Damen: Combat systems installation, trials completed on Indonesia’s 2nd SIGMA frigate

Authorities

Damen Shipyards Group and its partner PT PAL recently completed installation and testing of combat systems to the second of the Indonesian Ministry of Defence’s SIGMA 10514 Perusak Kawal Rudal (PKR) guided missile frigates, the KRI Gusti Ngurah Rai (332).

Photo: Damen

The PKR frigates are constructed via a modular process operating simultaneously at Damen Schelde Naval Shipbuilding (DSNS) in the Netherlands and the PT PAL shipyard in Indonesia.

This method enables Damen to fullfil its commitment to the Indonesian Ministry of Defence to deliver a knowledge and transfer of technology (ToT) programme.

A significant part of this transfer programme is the installation of combat systems along with provision of training to the crew in their usage and maintenance.

“From the outset of this project DSNS and our partner Thales Netherlands have been fully committed to the development of the Indonesian defence industry and its supporting sectors. This commitment is demonstrated with a series of ToT and local content programmes starting in 2013 when project execution commenced,” Hein van Ameijden, managing director of DSNS, commented.

The combat systems installed and tested include the following:

• VL MICA for defence from airborne threats;
• Exocet for defence from offensive targets at greater distance;
• Torpedo system for protection against submarine threat;
• 35mm rapid-fire cannon to respond to threats from both air and sea;
• Electronic detection system to divert enemy attacks with electromagnetic redirection;
• Modification of the computer operated operational system in order to operate the above.

The final phase prior to handover was successfully completed on February 21 with sea-going trials – the sea acceptance test (SAT). The purpose of this was to demonstrate that installations throughout the entire chain of weapons systems meet desired efficiency and accuracy.

“All our prior efforts paid off. Already at the start of the tests it was clear that installation had been carried out with great precision during construction and that preparatory alignment activities and agreements had been carefully followed.”

“The second PKR vessel achieved similar results to the first one. This demonstrates that the complete concept implemented in the SIGMA PKR Class can be considered reliable and robust,” Van Ameijden concluded.

The 105-metre, 2,365 tonne PKR frigates are designed to undertake a range of missions in and beyond Indonesian waters. Their primary mission is anti-air, anti-surface and anti-submarine warfare. However, they are also equipped for maritime security, search and rescue, and humanitarian support tasks.


Related:

Indonesian Navy commissions second SIGMA frigate KRI I Gusti Ngurah Rai

Indonesian Navy receives first SIGMA 10514 guided missile frigate