Sea Trials Delayed for USS Gerald R. Ford

Testing of advanced systems onboard USS Gerald R. Ford has fallen behind schedule, thereby delaying the sea trials phase.

The delay of the sea trials phase may add up to six to eight weeks and push the delivery of the US Navy’s new aircraft carrier behind the march 2016 deadline.

In a statement released yesterday, reported by Defense News, the US Navy has further stated that the exact delivery date will be known only after the completion of the sea trials phase.

What caused the delay is the CVN 78 shipboard test program. The Navy has acknowledged that the CVN 78 is 93% complete.

The news came in the wake of another possible delay which may be caused by shock trial tests requested by Michael Gilmore, Director, Operational Test and Evaluation. The shock trials could, by some estimates, prolong the carrier’s delivery date for up to two years.

Naval Today Staff, Image: US Navy

Share this article

Follow Naval Today

Events>

<< Nov 2017 >>
MTWTFSS
30 31 1 2 3 4 5
6 7 8 9 10 11 12
13 14 15 16 17 18 19
20 21 22 23 24 25 26
27 28 29 30 1 2 3

Maritime Information Warfare 2017

Maritime Information Warfare will focus on the growing need for navies to develop their information exploitation capabilities…

read more >

Maritime Reconnaissance and Surveillance Technology

Over the past few years, maritime intelligence gathering and ISR capabilities have returned to the forefront of the defence industry…

read more >

Sea-Air-Space 2018

Sea-Air-Space is now the largest maritime exposition in the U.S. and continues as an invaluable extension of the Navy League’s mission…

read more >